TemplatesOffice relocation
Office relocation project plan template
Moving an office is a classic waterfall project: a lease has to be signed before the fit-out, the fit-out has to finish before the move, and the move has to happen before the old space is handed back. Miss one hand-off and everything behind it slips.
This plan lays the whole move out as a work breakdown structure, with the dependencies that tie it together. Use it as a checklist for your own move. It is also Waterfall PM's sample project: create your own team when you sign up and a live copy is waiting in it — already under way, with planning done and the space plan in progress, so you can watch the schedule react as you change it.
- working days
- 30
- phases
- 4
- tasks
- 14
- milestones
- 3
How the plan fits together
Build-out drives the move
Contractor build-out is the longest task on the critical path: any delay to it delays the move, day for day.
Network starts partway in
Network & phone install starts a week after build-out starts — a start-to-start link with a week of lag — rather than waiting for the builders to leave.
Furniture lands at the end
Furniture delivery finishes when build-out finishes — a finish-to-finish link — so it arrives as the space is finished, not weeks into a building site.
Some work has room to slip
Update address everywhere is off the critical path: it has float, so it can slip without moving the move.
The full plan
Every task with its duration, when it starts and finishes (in working days from the start of the project), and its predecessors, written the way the Predecessors column takes them — what FS, SS and FF mean.
| # | Task | Duration | Starts | Finishes | Predecessors | Critical |
|---|---|---|---|---|---|---|
| 1 | Planning | 5 days | Day 0 | Day 5 | — | |
| 1.1 | Confirm budget & headcount | 2 days | Day 0 | Day 2 | — | Yes |
| 1.2 | Shortlist sites | 3 days | Day 2 | Day 5 | 1.1FS | Yes |
| 1.3 | Sign lease | Milestone | Day 5 | Day 5 | 1.2FS | Yes |
| 2 | New office fit-out | 20 days | Day 5 | Day 25 | — | |
| 2.1 | Space plan | 5 days | Day 5 | Day 10 | 1.3FS | Yes |
| 2.2 | Contractor build-out | 15 days | Day 10 | Day 25 | 2.1FS | Yes |
| 2.3 | Network & phone install | 4 days | Day 15 | Day 19 | 2.2SS+1w | — |
| 2.4 | Furniture delivery | 2 days | Day 23 | Day 25 | 2.2FF | Yes |
| 2.5 | Final walkthrough | Milestone | Day 25 | Day 25 | 2.2FS, 2.3FS, 2.4FS | Yes |
| 3 | Move prep | 8 days | Day 5 | Day 13 | — | |
| 3.1 | Notify staff & clients | 1 day | Day 5 | Day 6 | 1.3FS | — |
| 3.2 | Inventory & label equipment | 3 days | Day 6 | Day 9 | 3.1FS | — |
| 3.3 | Book movers | 2 days | Day 5 | Day 7 | 1.3FS | — |
| 3.4 | Pack departments | 4 days | Day 9 | Day 13 | 3.2FS | — |
| 3.5 | Update address everywhere | 3 days | Day 6 | Day 9 | 3.1FS | — |
| 4 | Move & settle | 5 days | Day 25 | Day 30 | — | |
| 4.1 | Move | 2 days | Day 25 | Day 27 | 2.5FS, 3.4FS, 3.3FS | Yes |
| 4.2 | IT setup & testing | 2 days | Day 27 | Day 29 | 4.1FS | — |
| 4.3 | Unpack & settle in | 3 days | Day 27 | Day 30 | 4.1FS | Yes |
| 4.4 | Old office handover | Milestone | Day 30 | Day 30 | 4.3FS | Yes |